Projects
S. Green Street and Sand Lane
Water and Sewer Relocation Project
Read more about it...

Traffic Detours
Beginning March 2, 2010
(Courtesy of The Gleaner
–
Tuesday, March 2, 2010)
Work continues on Green Street
Gleaner staff
Henderson Water Utility continues to install
a new 4-inch sewer main at Fair Street, and work also continues in the outside
eastbound lane of South Green Street near Ragan Avenue.
The construction near Ragan Avenue is for the
installation of a series of stormwater intakes that will carry stormwater to
Canoe Creek.
The inside eastbound lane of Green Street
will remain open to traffic at both construction locations. Both westbound
lanes will remain open to traffic throughout the construction areas.
The work is necessary for the utility
relocation portion of the Sand Lane widening project.
Eastbound traffic will merge to the inside
lane west of Fair Street and merge a second time to the inside lane near Sureway.
The westbound lanes will not be restricted, although motorists should slow down
and drive carefully.
Those with questions can call HWU at 826-2824
or go to the HWU Web site at www.hkywater.org
.
For further information, call the Henderson Water Utility at
(270) 826-2824.

Construction Project Location
The thick blue line represents the water transmission line
The thin yellow line represents the boundary of the
upcoming Combined Sewer Separation Project
|